Bidding Announcement

154.7MWac Romania Cotofeni Photovoltaic Project

Bidding Announcement (Second Round) for Owner’s Engineer Consulting Services

 

Project location: Romania

I. Bidding Conditions

This Romanian Cotofeni 154.7MWac Photovoltaic Project (comprising the following four companies: 1. JIUL FOTOVOLTAIC S.R.L.; 2. COTOFENI SOLAR PLANT S.R.L.; 3. DANUBE SOLAR SIX S.R.L.; 4. DOBRUNUS FOTOVOLTAIC S.R.L.) has been approved by the relevant project approval authorities. The project is funded through self-raised capital and loans, and the Bid Inviter is COTOFENI SOLAR PLANT S.R.L.   This project has met the bidding conditions and is now open for bidding.

II. Project Overview and Bidding Scope

  1. Construction Site: Cotofeni, Romania
  2. Scale: 154.7MWac PV Project
  3. Construction Period: 495 calendar days in total
  4. Term of the Owner’s Engineer Consulting Services: Tentatively set from October 15, 2026, to February 22, 2028; the specific commencement date shall be subject to the Owner’s notice. Total calendar days: 495 days.
  5. Bidding Scope: as shown in the following table
Lot name Bidding Scope
Owner’s engineer consulting services (Second Round) for 154.7MWac Photovoltaic Project in Cotofeni, Romania Review the construction drawings, construction organization design and special method statement), technical documents, acceptance data and equipment compliance certificates submitted by EPC Contractor of 154.7MWac Photovoltaic Project in Cotofeni, Romania (including supporting transmission lines, local booster stations, 20kV MV line relocation and burial on site, 110kV transmission lines and power grid reinforcement works, etc.); put forward professional review opinions and assist the Bid Inviter or EPC Contractor to improve the documents; ensure that all documents comply with Romanian legal requirements; carry out whole-process project management and construction supervision, including supervision and control of quality, safety, environmental protection, etc., connect with local authoritative testing and certification institutions in Romania, assist in completing equipment testing, project acceptance and other related work, ensure that the acceptance process meets local standards, and obtain acceptance certificates in time; assist the Bid Inviter and EPC Contractor to connect with the local competent authorities in Romania, and participate in the handling of construction permits, power grid access approval and other procedures; participate in the project construction process acceptance and project completion acceptance, supervise the acceptance process, check whether the project quality, safety, environmental protection and other aspects meet the relevant standards and contract agreements, issue acceptance opinions, and assist the Bid Inviter in handling the project completion acceptance filing procedures, organize the acceptance materials, submit the completion acceptance report, and ensure that the project passes the acceptance of the local Romanian competent authorities smoothly; prepare and submit the Owner’s engineer consulting service report and completion report as required.

III. Qualification Requirements for the Bidder

  1. The Bidder or company is a legal corporate organization legally registered in the EU, holds a legal person registration certificate issued within the EU, has the ability to bear civil liability, and has the right to enter into contracts;
  2. The Bidder is not included in the EU region credit blacklist, financial blacklist, judicial blacklist, tax blacklist and other situations that affect the implementation of this project.
  3. The Bidder is not within the penalty period for bidding prohibition confirmed by the relevant documents of the EU region administrative department or China Huadian Corporation Ltd.;
  4. Any legal person, other organization, or individual that has an interest relationship with the Bid Inviter and Bidder with the potential to affect the fairness of the procurement shall not be permitted to participate in the response. Different organizations which have the same organization leader, holding relation or management relation shall not participate in the response for the same lot or the response for the same bidding project with no divided lots.
  5. Bidders must possess valid local service qualifications in Romania and be capable of independently completing ISC project filing, personnel registration, statutory supervision duties, and official acceptance filing, as well as issuing supervision documents recognized by Romanian authorities. (Attach ISC-issued certificate, including DS certificate issued separately by ISC)
  6. The Bidder must have a track record of at least two (2) contracts for Owner’s Engineer (or supervision) services for photovoltaic power stations with a capacity of 45 MW or above located in Romania over the past 10 years (from January 1, 2016 to the bid submission deadline). Valid supporting documentation must be provided for all relevant contract performance records:

Main contract information: contract cover page, contract signature page, contract scope page or list page, or main technical requirements (parameters) page; or other materials capable of providing equivalent proof.

  1. Consortium bidding is not allowed for this project.

IV. Acquisition of Bidding Documents

Announcement Date: From 23 Sep 2026 to 27 Sep 2026

Announcement address: https://enero-furnizare.com/ website in Romania

Time for purchasing the bidding documents: From 23 Sep 2026

How to obtain:  Send the Letter of Participation in Bidding (See X. Letter of Participation in Bidding) to cotofeni.public@gmail.com. You will receive the Bidding Documents.

Contact person for obtaining bids: Ms Han.

Contact person for obtaining bids: Tel: +40 (733) 205885

V. Submission of Bid Documents

  1. Deadline for submission of bid documents: 11 October 2026..
  2. The Bid Inviter will reject the bid documents that are delivered late, not delivered to the designated location, or not sealed in accordance with the requirements of the bidding documents.

VI. Time and Place of Bid Opening

  1. Quotation opening time: 9:00AM 12 October 2026(Romania time).
  2. Place for opening quotation: Beijing online. The bidder shall send a legal representative or authorized agent (with supporting documents and ID card) to attend online.

VII. Channels and Methods for Raising Objections

If the bidder or other interested party has any objection to the announcement content of this procurement project, please raise it during the announcement period. This procurement project only accepts objections raised through the email address yinan-liu@chdoi.com.cn.

VIII. Supervision Department

If a bidder (supplier) or other interested party believes that the procurement activities do not comply with laws and regulations, they may file a complaint within 10 days from the date of knowing or should have known.

The supervision department of this procurement project is Huadian Overseas Investment Co., Ltd.

Purchasing supervision complaint acceptance email: caigoujiandu@chdhk.com. This procurement project will only accept objections raised through this email address.

IX. Contact Information

Bid Inviter: 1. JIUL FOTOVOLTAIC S.R.L.

JIUL FOTOVOLTAIC S.R.L.

  1. COTOFENI SOLAR PLANT S.R.L.

COTOFENI SOLAR PLANT S.R.L.

  1. DANUBE SOLAR SIX S.R.L.

DANUBE SOLAR SIX S.R.L.

  1. DOBRUNUS FOTOVOLTAIC S.R.L.

DOBRUNUS FOTOVOLTAIC S.R.L.

Address: TARGU JIU, str ISLAZ, no. 17, bl, sc, et. 1,ap.BIROUL 3 Gorj county

Contact person: Ms Han.

Tel: +40 (733) 205885

Email: cotofeni.public@gmail.com

X. Letter of Participation in Bidding

 

Letter of Participation from the Owner’s engineer consulting services for 154.7MWac Romania Cotofeni Photovoltaic Project
Bidder
Contact person of the Bidder
Tel. of contact person of the Bidder
E-mail of the Bidder
Deposit Bank of the Bidder
Bank code of the Bidder
Account name of the Bidder
Bank account No. of the Bidder
 

Bidder: (Seal)

Date:

Bidding Announcement

154.7MWac Romania Cotofeni Photovoltaic Project

Bidding Announcement for Owner’s Engineer Consulting Services

Project location: Romania

I. Bidding Conditions

This Romanian Cotofeni 154.7MWac Photovoltaic Project (comprising the following four companies: 1. JIUL FOTOVOLTAIC S.R.L.; 2. COTOFENI SOLAR PLANT S.R.L.; 3. DANUBE SOLAR SIX S.R.L.; 4. DOBRUNUS FOTOVOLTAIC S.R.L.) has been approved by the relevant project approval authorities. The project is funded through self-raised capital and loans, and the Bid Inviter is COTOFENI SOLAR PLANT S.R.L.   This project has met the bidding conditions and is now open for bidding.

II. Project Overview and Bidding Scope

  1. Construction Site: Cotofeni, Romania
  2. Scale: 154.7MWac PV Project
  3. Construction Period: 540 calendar days in total
  4. Term of the Owner’s Engineer Consulting Services: Tentatively set from September 1, 2026, to February 22, 2028; the specific commencement date shall be subject to the Owner’s notice. Total calendar days: 540 days.
  5. Bidding Scope: as shown in the following table
Lot name Bidding Scope
Owner’s engineer consulting services for 154.7MWac Photovoltaic Project in Cotofeni, Romania Review the construction drawings, construction organization design and special method statement), technical documents, acceptance data and equipment compliance certificates submitted by EPC Contractor of 154.7MWac Photovoltaic Project in Cotofeni, Romania (including supporting transmission lines, local booster stations, 20kV MV line relocation and burial on site, 110kV transmission lines and power grid reinforcement works, etc.); put forward professional review opinions and assist the Bid Inviter or EPC Contractor to improve the documents; ensure that all documents comply with Romanian legal requirements; carry out whole-process project management and construction supervision, including supervision and control of quality, progress, investment, safety, environmental protection, etc., connect with local authoritative testing and certification institutions in Romania, assist in completing equipment testing, project acceptance and other related work, ensure that the acceptance process meets local standards, and obtain acceptance certificates in time; assist the Bid Inviter and EPC Contractor to connect with the local competent authorities in Romania, and participate in the handling of construction permits, power grid access approval and other procedures; participate in the project construction process acceptance and project completion acceptance, supervise the acceptance process, check whether the project quality, safety, environmental protection and other aspects meet the relevant standards and contract agreements, issue acceptance opinions, and assist the Bid Inviter in handling the project completion acceptance filing procedures, organize the acceptance materials, submit the completion acceptance report, and ensure that the project passes the acceptance of the local Romanian competent authorities smoothly; prepare and submit the Owner’s engineer consulting service report and completion report as required.

III. Qualification Requirements for the Bidder

  1. The Bidder is a legal corporate organization legally registered in Romania, holds a legal person registration certificate issued by the Romanian government, has the ability to bear civil liability, and has the right to enter into contracts;
  2. The Bidder is not included in the Romanian credit blacklist, financial blacklist, judicial blacklist, tax blacklist and other situations that affect the implementation of this project.
  3. The Bidder is not within the penalty period for bidding prohibition confirmed by the relevant documents of the Romanian administrative department or China Huadian Corporation Ltd.;
  4. Any legal person, other organization, or individual that has an interest relationship with the Bid Inviter and Bidder with the potential to affect the fairness of the procurement shall not be permitted to participate in the response. Different organizations which have the same organization leader, holding relation or management relation shall not participate in the response for the same lot or the response for the same bidding project with no divided lots.
  5. Bidders must possess valid local service qualifications in Romania and be capable of independently completing ISC project filing, personnel registration, statutory supervision duties, and official acceptance filing, as well as issuing supervision documents recognized by Romanian authorities.
  6. The bidder must have a track record of at least three contracts for owner’s engineer (or supervision) services for photovoltaic power stations with a capacity of 50 MW or more located in Romania over the past 10 years (from January 1, 2016, to the bid submission deadline). Valid supporting documentation must be provided for all relevant projects:

Main contract information: contract cover, contract signature page, contract scope page or list page or main technical requirements (parameters) page.

  1. Consortium bidding is not allowed for this project.

IV. Acquisition of Bidding Documents

Announcement Date: From 28 July 2026 to 2 August 2026

Announcement address: https://enero-furnizare.com/ website in Romania

Time for receiving the bidding documents: From 28 July 2026.

How to obtain: Send the Letter of Participation in Bidding as X to stitch626lyc@gmail.com . You will receive the Bidding Documents.

Contact person for obtaining bids: Li Yanchen

Contact person for obtaining bids: Tel: +40 (746) 349822

V. Submission of Bid Documents

  1. Deadline for submission of bid documents: 18 August 2026.
  2. The Bid Inviter will reject the bid documents that are delivered late, not delivered to the designated location, or not sealed in accordance with the requirements of the bidding documents.

VI. Time and Place of Bid Opening

  1. Quotation opening time:9:00AM 19 August 2026(Romania time).
  2. Place for opening quotation: Beijing online. The bidder shall send a legal representative or authorized agent (with supporting documents and ID card) to attend online.

VII. Channels and Methods for Raising Objections

If the bidder or other interested party has any objection to the announcement content of this procurement project, please raise it during the announcement period. This procurement project only accepts objections raised through the email address yinan-liu@chdoi.com.cn.

VIII. Supervision Department

If a bidder (supplier) or other interested party believes that the procurement activities do not comply with laws and regulations, they may file a complaint within 10 days from the date of knowing or should have known.

The supervision department of this procurement project is Huadian Overseas Investment Co., Ltd.

Purchasing supervision complaint acceptance email: caigoujiandu@chdhk.com. This procurement project will only accept objections raised through this email address.

IX. Contact Information

Bid Inviter: 1. JIUL FOTOVOLTAIC S.R.L.

JIUL FOTOVOLTAIC S.R.L.

  1. COTOFENI SOLAR PLANT S.R.L.

COTOFENI SOLAR PLANT S.R.L.

  1. DANUBE SOLAR SIX S.R.L.

DANUBE SOLAR SIX S.R.L.

  1. DOBRUNUS FOTOVOLTAIC S.R.L.

DOBRUNUS FOTOVOLTAIC S.R.L.

Address: TARGU JIU, str ISLAZ, no. 17, bl, sc, et. 1,ap.BIROUL 3 Gorj county

Contact person: Li Yanchen

Tel: +40(746)349822

Email: stitch626lyc@gmail.com

X. Letter of Participation in Bidding

 

Letter of Participation from the Owner’s engineer consulting services for 154.7MWac Romania Cotofeni Photovoltaic Project
Bidder
Contact person of the Bidder
Tel. of contact person of the Bidder
E-mail of the Bidder
Deposit Bank of the Bidder
Bank code of the Bidder
Account name of the Bidder
Bank account No. of the Bidder
 

Bidder: (Seal)

Date:

 

Enero Furnizare, the Romanian energy trader & developer, has reached the third approved project of 75 MWp power installed and wants to reach 1 GWp solar project’s total power installed at the end of this year.

Enero Furnizare, the Romanian energy trader & developer, has gladly announced that it has reached the third approved project of 75 MWp power installed. The facility is made up of 125,000 bifacial solar panels and 325 solar inverters. The project is developing on land with approx. 84 hectares, in Dolj county, South of Romania, where the solar irradiation is about 1400 kWh/kWp/year.

According to the enero-furnizare.com website, the third project will deliver clean energy to the national grid starting with December 2023. The ENERO company is also developing another five solar projects, to reach 1 GWp solar projects total power installed at the end of this year.

https://www.pv-magazine.com/press-releases/enero-receives-connection-approval-for-its-third-solar-project-in-romania/

ENERO FURNIZARE, the Romanian energy trader & developer has received the connection approval of its second solar project 95 MW, located in Dolj county. Also, ENERO acquired the location, in Targu Jiu city-ROMANIA, for the development of its first gas to power project, with about 200 MW power installed, for balancing of the future solar power plants.

ENERO FURNIZARE, the Romanian energy trader & developer, has received the connection approval of its second solar project 95 MW, located in Dolj county, South of Romania. The facility is made up of 158,334 bifacial solar panels and 270 solar inverters. The project is developing on approx. 99 hectares land. The land has sandy soil which is brighter compared to normal soil and ensures a better sunlight reflection effect, optimally for the application of bifacial solar panels. According to the www.enero-furnizare.com website, the project will deliver clean energy to the national grid starting with December 2024.

The ENERO company is also in progress to develop other solar projects, to reach 1,000 MW total power installed, in the South & West of Romania, where the solar irradiation is at least 1,400 MWh/MWp.

On the other hand, ENERO acquired the location through an SPV, in Targu Jiu city-ROMANIA, for the development of its first gas to power project with about 200 MW power installed, especially for balancing of the future solar power plants.

ENERO FURNIZARE, the Romanian energy trader & developer has received the connection approval of its second solar project 95 MWp, located in Dolj county, South of Romania. The facility is made up of 158,334 bifacial solar panels and 270 solar inverters. The project is developing on approx. 99 hectares land. The land has a sandy soil which is brighter compared to normal soil and ensures better sunlight reflection  effect, optimally for the application of bifacial solar panels. The project will deliver the clean energy to the national grid starting with December 2024.

The ENERO company is also in progress to develop other solar projects, to reach 1,000 MW total power installed, in South & West of Romania, where the solar irradiation is at least of 1,400 MWh/MWp.

On the other hand, ENERO acquired the location through a SPV, in Targu Jiu city-ROMANIA, for development of its first gas to power project with about 200 MW power installed, especially for balancing of the future solar power plants.

Primul parc fotovoltaic dezvoltat de Enero Furnizare printr-o companie de proiect, de 71 MW, situat în județul Dolj, a primit aprobarea de conectare la rețeaua națională. Enero vrea să finalizeze până la sfârșitul anului viitor și alte 4 proiecte similare pe care le are în Dolj, cu o putere totală de peste 400 MW instalată, investiția totală fiind estimată la 300 de milioane de euro.
Totodată, Enero intenționează să se lanseze și în dezvoltarea altor proiecte fotovoltaice în Oltenia și Banat , cu o putere agregată de 600 MW, pentru a ajunge la proiecte solare de 1 GW la sfârșitul acestui an. Investiția totală estimată pentru atingerea puterii instalate de 1 GWp este de aproximativ 700 milioane euro.

“The project will deliver clean energy to the national grid starting with December 2023. The ENERO company is also developing another five solar projects with more than 400 MWp total power installed, in the South of Romania, where the solar irradiation is at least 1,400 MWh/MWp. At the same time, ENERO is in progress to start the development of other big solar projects, with aggregated power of 600 MWp, to reach 1 GWp solar projects at the end of this year.”

ENERO FURNIZARE, the Romanian energy trader & developer has formally announced it had received the connection approval of its first solar project 71 MW DC/49 MW AC, located in Dolj county, South of Romania. The facility is made up of 120,340 bifacial solar panels and 266 solar inverters. The project is developing on approx. 80 hectares land. The land has a sandy soil which is brighter compared to normal soil and ensures better sunlight reflection effect, optimally for the application of bifacial solar panels.
The project will deliver the clean energy to the national grid starting with December 2023. The ENERO company is also developing another five solar projects with more than 400 MWp total power installed, in South of Romania, where the solar irradiation is at least of 1,400 MWh/MWp. At the same time, ENERO is in progress to start the development of other big solar projects, with aggregated power of 600 MWp, to reach 1 GWp solar projects at the end of this year.